How much work is in a first product release?

Build a first-pass MVP estimate from one user journey, a range of delivery effort and the ongoing costs your team will carry after launch.

Estimate a journey people can complete

Take a booking enquiry as an example. A visitor finds a listing, selects a date, sends a request and receives an acknowledgement. A provider reads it and responds. Include the operator who handles a missed email or an unavailable room. A list of screens alone would miss both jobs.

Separate known work from the unknowns

Write down the smallest acceptance example for each part. Estimate effort as a range, then list dependencies separately. Waiting for access to a provider system can delay launch even if the integration takes only a day to build.

Work through a sample budget

For illustration, allow 2–3 person-days to define the journey, 3–5 for the interface, 4–8 for implementation and 2–4 for testing and handover. That gives 11–20 person-days. Multiply the range by your quoted day rate, then add direct expenses and any applicable tax. These example effort figures describe this exercise only.

Turn effort into a calendar

Mark the review dates, content delivery and external approvals alongside the work. A team that has two days a week available needs at least six weeks to supply eleven person-days. Revisit the range after the largest unknown has been tested.

What to ask for in a quote

Ask the supplier to identify which roles, devices, integrations and handover materials are included. Keep future recurring costs on their own line so the launch budget and the running budget are both visible.